The project


  • Length: 11.2 km
  • 18 traveler stations
  • Total invesment cost: €228 million, including €118 million controlled by RATP
  • Notable features of the project included complex time management, due to the number of contracting authorities for the platform (six), led by RATP, and the location (across two French departments: Val-de-Marne and Essonne).
  • The rights of way covered different terrain:
    • Roads: RD7 and RN7
    • An airport: Orly
    • Industrial zones:
      • Semmaris
      • Sogaris
      • Silib
    • Urban areas

Key data



ClientRATP
PeriodeDec. 2004 - Dec. 2013
Cost 228 000 000 €

Gestion de l'Association pour la Gestion des Dépenses Communes des Lotissements (A.G.D.C.L)


 

Our roles


planitec btp provided scheduling, construction management and coordination (SCMC) services on behalf of RATP, the coordinator of the seven contracting authorities for the project.

The assignment covered the design and implementation phases (preliminary/detailed design, as well as assistance with bids, works supervision and acceptance) up to the commissioning of the tramway.

This involved two simultaneous roles:

  • Assisting RATP with the coordination of multiple contractors (overall scheduling and coordination)
  • Providing SCMC services for RATP’s own construction work

Each planitec btp service followed RATP’s quality management plan, which required a monthly project and progress review.

More infos